Concreting the shed
April 27th, 2008
After pumping water into the new tank, the next project on the list was the new shed. It is a bit embarrassing to talk about this storage area as a “shed” in a place where sheds usually span at least six metres and are composed of three or more, three metre bays but we had bought as big as we could without having to get council approval to build it.
So the “shed” was three metres by three metres and would do to house mowers and garden tools and get a heap of other stuff out of the way.
A trip into Clare to buy cement was an opportunity, as always, for Raph to get a pie and we loaded 16 bags of cement into the trailer from Mitre10.
With that amount of cement, we needed a heap of gravel. Consulting our new “How to make concrete” booklet, we worked out that we’d need at least two trailer loads of sand/gravel mix. Erring on the side of caution for a change, and with the quarry closed over the long weekend, Raph and I did three quick trailer loads before tackling the pre-pack shed.
It was a bit of a laugh how easy it was to zip the shed together. Even though the wind came up, the two of us managed to hold and fix walls together and then fit the roof. Thanks to Raph’s ingenious use of straw bales as a “third person” to support a wall, we were soon admiring out work.
Of course, our haste to build the shed saw us erect it next to where we wanted it to live, and the next morning with a bit of grunting and a little bending, Meg, Raph and I man-handled it into position to prepare for the concreting.
Being an opportunistic scavenger, I had leftover reinforcing from when the “real” shed was professionally concreted and this was enough to cover the floor with a little overlap outside. Using leftover pavers to lift the reo off of the ground and then the shed off of the reo gave us about 100mm for the concrete slab.
After Meg and I returned from the ANZAC Day dawn service in Clare, Raph and I set to work to mix the concrete with the resurrected mixer. I shovelled while Raph carted, spread and finished. We worked hard and fast with the threat of rain and in a couple of hours, the inside was finished.
Tired after the early start and hard labour we retired for afternoon as the rain spoiled any chance of further work and the goon started to flow.
24mm of rain fell on Friday arvo and through Saturday and it was Sunday afternoon before Meg and I set to work to concrete the outside apron around the shed. Of course, as soon as we finished more showers came in, but the overall result will be functional.
The last few days have seen both a flurry of activity and construction as well as some relaxing DVD time, listening to the rain on the shed roof.


